Our experience, engineering, and planning make the difference.
When the largest electronics company in the world needed help, they selected our small family owned company to complete the difficult task of delivering a completed liftable building every six days.
From the October purchase order date to the first delivered building in December, CID was able to mobilize our second manufacturing plant, contract to local material suppliers, and gear up our work force for the 18 month continuous delivery schedule.
CID was able to coordinate with our customer lag times to manufacture and construct the buildings to match their electrical equipment lead times and testing schedules.
DAY 1
Staged Rooftop Sections & Structural Steel Platforms

DAY 2
Merge Rooftop Sections

DAY 3
Customer Equipment Mounted & Secured

DAY 4
Merge Rooftop with Building Base Frame

DAY 5
Building Weatherproofed & Roof Rubberized

DAY 6
Load and Ship Building

States We Work In:
Alabama, Arkansas, California, Colorado, Connecticut, Delaware, Florida, Georgia, Idaho, Illinois, Indiana, Iowa, Kentucky, Louisiana, Maine, Maryland, Massachusetts, Mexico, Michigan, Mississippi, Missouri, New Hampshire, New Jersey, New Mexico, New York, North Carolina, North Dakota, Ohio, Pennsylvania, Rhode Island, South Carolina, South Dakota, Tennessee, Texas, Vermont, Virginia, West Virginia, Wisconsin, Canada, Mexico, and other worldwide installations.

